| 20% |
On Agreement |
| 15% |
01-06-2011 completion of foundation |
| 10% |
01-08-2011 completion of 1st Slab |
| 10% |
01-10-2011 completion of 2nd Slab |
| 10% |
01-12-2011 completion of 3rd Slab |
| 10% |
01-02-2012 Bricks work and plastering |
| 10% |
01-04-2012 Plumbing and Electrical |
| 10% |
01-06-2012 Flooring and painting |
| 5% |
01-08-2012 Other finishing works |